Transmission gaps will prolong electricity instability
Ghana’s power instability will persist for at least two years. Energy analyst Kwadwo Poku warns that current power challenges could last for two years due to inadequate investment in electricity transmission infrastructure over the past two years. He says the country will likely contend with these difficulties for another two years because of the time required to award contracts and complete necessary infrastructure. The Energy Minister announced an allocation of 500 million for transmission infrastructure under the new economy, but Poku questions how quickly this funding will translate into completed projects due to the lengthy process of awarding contracts and completing the necessary work. He notes that the government cancelled an agreement with German development bank KfW and delayed acting on a 50 million World Bank funding arrangement for the transmission sector. This lack of progress remains evident in the K1 and K2 transmission lines, which were awarded in July 2024 and remain under construction. The Anwomaso – Ahodwo transmission line, part of these projects, remains incomplete even though the contract was awarded more than two years ago. Poku notes that the government inherited two such agreements when it assumed office in January 2025. He says, "The problem is the lack of investment in the last two years in the transmission." He argues that even if the government provides fresh funding to GRIDCo, the process of developing and completing transmission lines requires considerable time because the country cannot expect immediate improvements after announcing new budgetary allocations.
| Financial and Technical Data | Value |
|---|---|
| 2027 Budget Allocation | 500 million |
| World Bank Funding | 50 million |
| Inherited Generation Deficit | 700 megawatts |
Weather and technical faults trigger supply gaps
Minister for Energy and Green Transition John Jinapor attributed recent electricity supply disruptions to extreme weather and technical issues with gas infrastructure. He identified excess heat from El Nino and a technical problem at the gas infrastructure as factors that caused the disruptions. The gas infrastructure problem affected backup pumps and required the replacement of specialized equipment before production could increase. The replacement process was complicated by the time required to procure and install specialized equipment. Jinapor also disclosed that illegal chainsaw operators felled a tree onto a transmission line in the Kumasi area, which caused supply interruptions. He said the fault has since been addressed. He insists the country is not experiencing load shedding, though he admitted that a few pockets still face difficulties. The government inherited a generation deficit of approximately 700 megawatts because several power plants missed routine maintenance schedules. Maintenance works bring generating units back into operation, including the KTPP plant. Jinapor appealed to consumers to exercise patience while engineers work to resolve the remaining isolated disruptions. He expressed confidence that these interventions will strengthen supply reliability and prevent temporary technical difficulties from becoming a wider electricity crisis.