NYA aims to complete Azumah Nelson Sports Complex by 2027

NYA aims to complete Azumah Nelson Sports Complex by 2027

Funding and construction resumption

The National Youth Authority (NYA) aims to finish the Azumah Nelson Sports Complex in 2027. Osman Ayariga, the NYA Chief Executive Officer, expects the football pitch to be usable by the end of 2026. I find the project’s history of stagnation due to unpaid debts to be a clear sign of poor administrative planning. Ayariga told the Daily Graphic that the current administration inherited a contract that stalled because the contractor had outstanding certificates and lacked funds. This financial neglect forced the contractor to leave the site. The contractor has since returned to the site to work on the tartan track. The NYA allocated GH¢5 million from its 2026 capital expenditure toward the project and earmarked GH¢10 million from its 2027 capital expenditure for the rest.

Budget Item Amount
2026 CAPEX allocation GH¢5 million
2027 CAPEX allocation GH¢10 million
Total annual CAPEX GH¢20 million

The NYA expects the pitch to be available for football by the end of 2026, and Ayariga said he is hoping that "at least the pitch will be available already" while workers finish ancillary construction like the stands, tartan tracks, and pavements.

Status of regional youth centres

Boxing legend Azumah Nelson visited the site on several occasions. He visited when the complex sat abandoned and again when reconstruction began. He told the NYA he is waiting for the completion of construction so he can meet the media on the pitch. Ayariga noted that the sports complex falls under the NYA while the stadia fall under the Ministry of Sports, and both could run concurrently. Regarding the wider network of 10 Youth Resource Centres at various stages of completion, only two are fully completed. I think the situation with the other facilities is frustrating because they are being used but remain stuck in limbo due to paperwork. He noted that facilities in the Central and Western regions are currently in use, but they have not reached 100 per cent completion for handover because the NYA must wait to order and pay pending certificates. Ayariga expressed optimism that the complex and the remaining centres will be completed.